Aggreko commissions 30MW power rental project in Ethiopia
- Severe drought in Ethiopia caused hydro power shortages in
2008
- Aggreko commissioned a 30MW rental power project in Nazaret
within two months
- The rental power package will assist the local utility to meet
demand despite temporarily limited capacity
Nazaret, Ethiopia, March 2009 - Aggreko, the
global leader in the provision of rental power and temperature
control services, has successfully designed, mobilised, installed
and commissioned a 30MW power project for the Ethiopian
Electric Power Corporation (EEPCO). Due to power shortages in the
country, additional capacity was urgently needed, and Aggreko was
able to complete the project within two months of contract
signature.
Power in Ethiopia is almost exclusively generated by
hydro-electric power stations; at present, hydro accounts for 95%
of the country’s power capacity. However, severe droughts in 2008
reduced water levels at many dams, causing the power stations to
operate at lower efficiencies and resulting in power shortages and
vastly increased power demand. Currently EPPCO is in the process of
constructing four additional hydroelectric power stations, but the
stations are not due to be completed for several years. In order to
limit the impact of the power shortfall, EEPCO contracted Aggreko
to provide the 30MW/15kV rental power package.
The power package is connected directly to the EEPCO national
grid and is a turn-key operation, which will be staffed 24 hours a
day by Aggreko technicians. All design, engineering, mobilisation,
installation and commissioning was performed directly by Aggreko.
The company is also providing all operations and maintenance
servicing during the life of the project, in addition to project
decommissioning when the additional capacity is no longer
needed.
Steve Aitken, Managing Director of Aggreko Africa,
commented on the project: “The project marks Aggreko’s
first contract in Ethiopia and we are very pleased to further
expand our presence in East Africa. Although the time-scale was
very short, we worked closely with EEPCO to ensure that the power
package was up and running as soon as possible.” He added:
“Aggreko always strives to ensure that the local community
benefits from our presence in country and the same will be
applicable in Ethiopia. Aggreko has already recruited local
technicians whom we have sent to our centre of excellence for
specialist training.”
Jana Single
Aggreko International
PO Box 17576,
Jebel Ali,
United Arab Emirates
Tel: +971 4 883 4059
Fax:+971 4 883 5404
Editors
notes