Power to Cement Manufacturers
Power to the Cement Manufactures
The challenge to the customer
Unprecedented population growth and
construction boom throughout the UAE caused an extraordinary leap
in demand for cement. Ras Al Khaimah a key site for development in
UAE, had plans to increase power capacity for their city to support
this progress. Whilst governmental plans were underway, some
manufacturing companies required immediate power to continue
their production.
Aggreko's solution
Aggreko was contracted to
supply 10 MW of temporary power, however within two months of
supplying the initial package a further 10 MW power
package was installed.
Aggreko power was used
to ensure that production levels of the cement
plant were achieved and maintained to meet the high demand of
cement in U.A.E.
The benefits to the customer
Abdo Nemer, General Manager of
Union Cement Company, commented: 'The power package provided by
Aggreko ensures that we have the power we need to meet our
production targets. We have been very pleased by both the
professionalisim and skill of the Aggreko team.