Industrial Heating for Motorway Construction
Tunnelling conditions in a time sensitive motorway project were
causing difficulty. Humidity and cold temperature within the
tunnel were delaying the painting of the tunnel surfaces. An
essential requirement was to raise temperature and dry out the
tunnel environment.
Oil Fired Heaters
To keep the project on track, Aggreko supplied four 125Kw oil
fired heaters, which deliver hot, dry air. Eight 5,000 cfm
air movers ensured this dry air reached all parts of the
tunnel. An Aggreko diesel generator
provided the electrical power required.
Benefits to the Customer
Dampness within the tunnel was rapidly reduced, and ambient
temperature raised. The painting was able to proceed to
schedule, bringing the project to a successful conclusion.